How Long Does It Take to Design and Build a House in Tasmania?

"When can you start?"

It's usually one of the first questions I'm asked. And I get it. Once you've decided to build, you want to get going.

But most people are surprised by how much happens before a builder sets foot on site.


THE SHORT ANSWER

Allow around 18 months to 2 years, from first enquiry to moving in.


Here's a look at what's involved in designing and building a home in Tasmania, whether it's a new build or a major renovation, and why it takes the time it does.

At a glance

  • Getting started: a few weeks to a month

  • Waitlist + site information: 3 to 6 months

  • Concept design

  • Planning approval: if required

  • Documentation + permits: often a year or more all up

  • The build: your builder's program

STAGE 1

Getting started

We meet to understand your site, brief and budget. I write a fee proposal so you know what's included and what it costs.

Time so far: usually a few weeks to a month.

STAGE 2

Waitlist + site information

Most building designers can't start your project tomorrow. Expect to wait at least three months, often longer.

We can often order some of the earlier consultant reports while you wait.

Time so far: 3 to 6 months.

There's a lot that goes on behind the scenes

Here are some of the most common consultants that may need to be involved before your home can be approved.

Land Surveyor: 4 to 8 weeks

Geotechnical Engineer: 4 to 6 weeks

Bushfire Assessor: 3 to 6 weeks

Wastewater Consultant: 6 to 8 weeks

Structural Engineer: 3 to 8 weeks

Energy Assessor: 2 to 3 weeks

Building Surveyor: 2 to 3 weeks


THE GOOD NEWS

You don't have to chase any of them. That's my job.


home_design-perth_tasmania

STAGE 3

Concept design

This is where your home takes shape: layout, form, how it sits on the site and how you'll live in it. It includes: design reviews, preliminary engineering and early builder pricing so we know the design is within your budget before we go any further.

Your feedback and decisions matter here too, and can have a real effect on how long this stage takes.

STAGE 4

Planning approval

If you need a planning permit, council has 28 days for permitted and 42 days for discretionary applications.

STAGE 5

Documentation + permits

Interiors, selections and the full drawing set your builder prices and builds from.

A building surveyor then reviews it all before the permit authority issues the building and plumbing permits.

Time so far: often a year or more.

THEN

The build

Your builder starts when their schedule allows, then works to their own program. That's why I encourage builder and trade input early in the design process.

All up: an estimated 18 months to 2 years, from first enquiry to moving in.

A comprehensive, thoughtful approach takes longer at the start, but it's worth it.

Time spent before construction gives you a resolved design, better documentation, a more accurate building contract and fewer variations on site.

I design the building and interiors together, coordinate the consultants and approvals and keep each stage clear, so you always know what comes next.

Not every building designer handles the whole process. If yours doesn't, that time doesn't disappear. It just lands on you.


If you're thinking about building in the next 12 to 18 months, now's the time to get in touch.

 

Frequently asked questions

 
Tahleah Hoyle

Licensed Building Designer and Interior Designer (B. Architecture and Built Environments) based near Launceston, designing new homes, major renovations and extensions across Northern Tasmania.

https://www.tahleahhoyledesign.com.au
Next
Next

Why the Right Team Matters in Home Design